Private condominium, Ipoh Lane, Singapore

During the construction phase of a condominium, some private residential bungalows at Thiam Siew Avenue encountered cracks on walls, ceilings, walkway and driveways on the premises during the process of foundation and pilling work.


The cracks were caused by the movement of the column footings due to soil movement caused by the neighbouring foundation work, resulting in the loss of load bearing capacity of the soil.


Uretek® applied deep injection method to create a resin barrier next to the sheet-pile so as to stop the soil movement and prevent the continuing movement of the footing foundation at the neighbouring houses.